Buying land and building on it is very doable in North Carolina. Doing things out of order is what costs people money. Here is the order that works, from people who sell rural land in NC.
Before you buy the land
- Make the offer contingent on a soil evaluation. In NC, your county Environmental Health office has to approve a septic site before you can get a building permit. If the soil won’t perc, the lot may not be buildable, or it may need an expensive engineered system. The NC Offer to Purchase lets you build in a due diligence period for this.
- Check zoning and minimum lot rules with the county planning office: setbacks, whether barndominiums or metal homes are allowed, and any subdivision restrictions or HOA covenants.
- Check the deed and plat for easements, road frontage and legal access. Landlocked land is hard to finance and hard to build on.
- Look up flood zones on the NC Flood Risk Information System (fris.nc.gov).
- Ask the power company how far the nearest line is and what it costs to bring service in.
Step 1: Survey
A licensed land surveyor marks your boundaries and, if needed, prepares the site plan the county asks for with the septic application. On a new split, the survey is required to record the new lot.
Step 2: Soil evaluation and septic permit
Apply to your county Environmental Health office for an Improvement Permit. A soil scientist evaluates the site and assigns the system type and the number of bedrooms allowed. Then you get a Construction Authorization. NC’s rewritten on-site wastewater rules (15A NCAC 18E) took effect on January 1, 2024, and some systems can now be designed by private licensed soil scientists or engineers. Ask your county which paths it accepts and how long each takes. Wait times range from weeks to months.
Your septic permit sets your house. The bedroom count and the house’s location on the lot come from this step, so finish it before final plans.
Step 3: Well permit and drilling
Most rural NC counties require a well construction permit from Environmental Health before drilling. The well must meet setbacks from the septic system and property lines. Hire an NC-certified well contractor, and plan to have the water tested once the well is in.
Step 4: Clearing, driveway and pad
A land clearing contractor clears the house site, septic area and driveway, then grades the pad. Don’t let equipment drive over the approved septic area, because compacted soil can void the permit. On a state road, you may need an NCDOT driveway permit.
Step 5: Building permit and builder
With the septic and well approvals in hand, your builder applies for the building permit. Any NC project of $40,000 or more needs a licensed general contractor. You can check a builder’s license at the NC Licensing Board for General Contractors. Each builder listing here shows what we found on the board and the date we looked.
Step 6: Septic installation and final inspections
A certified septic installer puts the system in according to your permit, and Environmental Health inspects it. The house gets its building inspections, and you receive a Certificate of Occupancy.
Quick checklist
- Due diligence period long enough for a soil evaluation
- Zoning, setbacks and restrictions confirmed
- Legal access and road frontage confirmed
- Flood zone checked
- Power availability and cost
- Boundary survey
- Septic Improvement Permit and Construction Authorization
- Well permit, then the well drilled and tested
- Clearing, driveway (NCDOT permit if needed) and pad
- Building permit with a licensed GC
- Septic installed and inspected
- Certificate of Occupancy
Rules vary by county, so call the county Environmental Health and planning offices early. They’re usually very helpful when you ask before you buy.
Sources and method
This guide is general information, not legal, engineering or lending advice. We print a figure only when we can name its source and date. Found something wrong? Tell us. How we work.